R-09Template / Job cost control

Construction job costing spreadsheet: cost to complete

Once work starts, the question is no longer what you planned to spend but what this job will finally cost. This spreadsheet projects final cost line by line from what is already invoiced, what is committed but not yet invoiced, and what still needs to be bought.

CSV file, opens in spreadsheet apps. Contains: Budget, actual, commitment, invoiced-against-commitment, estimate-to-finish and variance columns. Plain cells, not an automated workbook; enter or recreate calculations using the instructions. Example rows are hypothetical. Free, no login.

Use this when

  • A job is underway and you want to know if it is heading over budget while there is still time to act.
  • You have purchase orders and sub contracts that are partly invoiced.
  • Your accounting report shows spending to date but not what is still coming.

The double-counting trap

A $12,000 drywall subcontract is a commitment. When the sub invoices $7,000, that $7,000 is now an actual cost. The remaining commitment is $5,000, not $12,000. If you add actual costs to the full original commitment, you count $7,000 twice and the job looks $7,000 worse than it is. Every row must reduce the open commitment by what has been invoiced against it.

The rule this template uses: Projected final cost = actual cost to date + remaining open commitment + estimated cost to finish that is not yet committed. Remaining open commitment = committed amount - invoiced against that commitment.

Estimate to finish needs judgment

For uncommitted work, ask the person closest to it. If framing labor is 60% spent but the crew lead says the work is 40% done, do not assume the remaining 40% of budget is enough. Record the estimate to finish as a separate number with a date and who provided it.

  • Variance = approved budget - projected final cost. Negative means projected overrun.
  • Approved budget = original baseline + approved change order costs.
  • Pending changes stay out until approved, consistent with your change log.

How often to update

Weekly works for most residential jobs: enter new supplier and sub invoices, update commitments for any new purchase orders, and ask the job lead for a fresh estimate to finish on labor lines. Note the date of every update at the top. A projected overrun found in week three of a twelve-week job can still be managed through scope conversations, change orders or crew planning. The same overrun discovered at closeout is just a loss.

Worked example

Hypothetical
Hypothetical example: Hypothetical cost-to-complete lines (illustrative figures only)
LineBudgetActualCommitInvoiced vs commitOpen commitTo finishProjected
Drywall sub$12,400$7,000$12,000$7,000$5,000$0$12,000
Framing labor$18,600$11,300$0$0$0$9,100$20,400
Windows$9,800$9,640$9,640$9,640$0$0$9,640

Drywall: actual $7,000 + open commitment $5,000 = $12,000. Adding the full $12,000 commitment to actuals would wrongly show $19,000.

Step by step

  1. Copy the approved budget lines, including approved change orders, from your baseline.
  2. Enter actual invoiced or paid costs to date for each line.
  3. Enter committed amounts (subcontracts, purchase orders) and invoiced-against-commitment.
  4. Calculate remaining open commitment for each line.
  5. Enter an estimate to finish for uncommitted work.
  6. Calculate projected final cost and variance.
  7. Review lines with the biggest negative variance first and decide what to do.

Common mistakes

  • Adding full commitments to actual invoices.
  • Assuming remaining budget equals remaining cost.
  • Including unapproved changes in the approved budget.
  • Waiting until the job is finished to look at variance.

Limits of this resource

  • The spreadsheet does not reconcile to your accounting system; mapping costs to jobs correctly is still required.
  • Projected cost is only as good as the estimate to finish entered.

Cost-to-complete worksheet

talon-job-cost-to-complete.csv

Download CSV