Construction change order log

One change order is a document. Ten change orders on the same job is a register, and the register is where money gets lost. This log tracks every change by status so pending requests never get counted as contract value and approved ones never get forgotten at billing time.

CSV file, opens in spreadsheet apps. Contains: Status-based register with evidence, billing reference and totals guidance. Plain cells, not an automated workbook; enter or recreate calculations using the instructions. Example rows are hypothetical. Free, no login.

Use this when

  • A job has more than two or three changes in play at once.
  • You need to tell a homeowner or lender the current contract value with confidence.
  • Approved changes keep getting missed on the next invoice or draw.

Status is the most important column

Use a small fixed set of statuses and do not invent new ones on the fly: Draft, Proposed, Approved, Rejected, Withdrawn, Billed. Each row has exactly one status at a time. A change moves from Proposed to Approved only when you hold approval evidence in the form your contract requires, and the log records what that evidence is and where it is filed.

Rejected and withdrawn changes stay in the log. Deleting them removes the history of why scope did not change, which matters if the same request comes back or a dispute arises.

Three totals, never one

Keep three separate totals at the top: approved changes, pending (proposed) changes and rejected changes. Current contract value equals original contract plus approved changes only. Pending exposure is a separate number that tells you how much could change. Adding pending items to the contract value is the most common mistake in homemade change logs and it overstates what you can bill.

Billing status is separate again. An approved change can be unbilled, partly billed or fully billed. Record the invoice or draw reference so the same change is not billed twice, once on its own and again folded into a later draw.

Cost side

Record the estimated cost of each change alongside its price so you can see the margin on change work. When a change is approved, add the cost to your job budget as a new line with the change number. That keeps the original baseline intact while the cost-to-complete reflects reality.

Worked example

Hypothetical
Hypothetical example: Hypothetical kitchen remodel change log (illustrative figures only)
CODescriptionStatusPriceEvidenceBilled
CO-01Add under-cabinet lightingApproved$1,340Signed change docDraw 3
CO-02Upgrade to quartzProposed$2,950Awaiting reply-
CO-03Relocate sink 18 in.Rejected$1,780Owner email declined-
CO-04Replace rotted subfloorApproved$865Signed change docNot yet

Approved total: $2,205. Pending: $2,950. Rejected: $1,780. Current contract value adds only the $2,205.

Step by step

  1. Enter the original contract value at the top.
  2. Add a row for every request as soon as it is raised, starting at Draft or Proposed.
  3. Link each row to its preparation worksheet or change document.
  4. Update status only with evidence, and record the evidence type and date.
  5. Recalculate approved, pending and rejected totals separately.
  6. Record billing references when approved changes are invoiced.
  7. Review the log with the job lead weekly.

Common mistakes

  • Adding pending changes to the contract value.
  • Deleting rejected rows.
  • Billing a change separately and again inside a later draw.
  • No reference to where approval evidence is stored.

Limits of this resource

  • The log records status; it does not establish whether an approval is legally sufficient. Follow your contract and local requirements.
  • CSV formulas are not included. Totals are described in the instructions so they work in any spreadsheet app.

Change order register

talon-change-order-log.csv