Construction draw schedule template
A milestone draw schedule tells everyone what work earns which payment. This worksheet keeps four different facts apart that often get blended into one column: the planned share of the contract, the approval of the draw, the invoice you sent, and the money that actually arrived.
CSV file, opens in spreadsheet apps. Contains: Instructions row, milestone, share, approval, invoice and receipt columns, four hypothetical draws. Plain cells, not an automated workbook; enter or recreate calculations using the instructions. Example rows are hypothetical. Free, no login.
Use this when
- You are setting up a new custom home or major remodel and need to agree on payment milestones before work starts.
- A lender or homeowner asks for a draw schedule tied to inspectable progress.
- You keep thinking a draw is paid when it was only approved or invoiced.
Why approval, invoice and receipt need their own columns
On a construction-loan job, a draw usually moves through stages. The milestone is reached, someone inspects or reviews it, the draw is approved, an invoice or draw request is issued, and funds eventually land. Each stage can take days, and each can stop. A lender can approve a draw and still hold back a portion. A homeowner can pay part of an invoice. If one spreadsheet column says "Draw 3: $42,000" and nothing else, nobody can tell which stage that number describes.
The template therefore records the planned amount, the approved amount, the invoiced amount and the received amount separately, with a date and a reference for each. Outstanding is a calculation: invoiced minus received. It is never typed in by hand.
Choosing milestones that can be verified
Good milestones are events a third party could confirm on a site visit: foundation poured and inspected, framing complete and passed, dried-in, rough mechanical inspections passed, drywall hung, cabinets set, final inspection. Weak milestones are vague ("50% complete") or depend on your own internal progress estimate.
Keep the sum of all draw shares equal to 100% of the current contract value. When approved change orders add value, either add a separate change-order draw line or re-spread the remaining draws, and note which you chose. Never silently change a draw that has already been invoiced.
- Front-loading draws beyond the value of completed work can create disputes and may conflict with lender rules.
- Retainage, if your agreement uses it, belongs in its own column so that the withheld portion is not mistaken for a short payment.
- Deposits taken before work starts should be recorded as their own line with its own terms.
Partial payments and holdbacks
If a draw is approved at $40,000 but $36,000 arrives, record $36,000 received and leave the $4,000 outstanding with a note explaining why: inspection item open, retainage, lender fee deduction, or simple short payment. Do not change the invoiced amount to match the money. The gap is information you need to chase.
Worked example
Hypothetical| Draw | Milestone | Share | Planned | Invoiced | Received | Outstanding |
|---|---|---|---|---|---|---|
| 1 | Foundation inspected | 10% | $42,000 | $42,000 | $42,000 | $0 |
| 2 | Framing passed | 20% | $84,000 | $84,000 | $75,600 | $8,400 |
| 3 | Dried-in | 15% | $63,000 | $63,000 | $0 | $63,000 |
| 4 | Rough-ins passed | 15% | $63,000 | - | - | - |
Draw 2 shows a partial receipt: the $8,400 gap stays visible until it is explained or collected. Draw 3 is invoiced but not paid, so it is not cash.
Step by step
- Enter the current contract value at the top of the sheet and list draws in the order they are expected.
- Give each draw a verifiable milestone and a planned share. Confirm shares total 100%.
- When a milestone is reached, record the inspection or review date and what evidence supports it (photos, inspection card, lender inspection).
- Record the approved amount only after written approval arrives. Approval is not payment.
- Record the invoice or draw request number, date and amount.
- Record each receipt separately with date, method and reference once it is confirmed in the bank, not when someone says it was sent.
- Review outstanding amounts weekly and carry notes forward until each draw is closed.
Common mistakes
- Marking a draw "paid" when the lender emails an approval.
- Editing an issued invoice amount to match a short payment, which erases the shortfall.
- Letting change orders inflate draws without a written record of how they were spread.
- Using percent-complete guesses as milestones that nobody else can verify.
Limits of this resource
- This worksheet is a planning and tracking aid. It is not a loan document, lien waiver or contract term, and lender requirements differ.
- Confirm draw procedures, retainage and inspection rules with your lender, contract and local requirements.
Draw schedule worksheet
talon-construction-draw-schedule.csv
Related resources
Related TALON pages
- Job schedule and billing draws — How TALON places scheduled draws on a job timeline.
- Job billing review — How approved scope, invoices and receipts stay separate inside TALON.
Connect field work to the books
TALON brings estimates, jobs, schedules and cash into one view for small builders and remodelers.