Construction cash flow forecast: what happens if one payment is late?
Most cash problems on a residential job are timing problems, not profit problems. A job can be priced well and still leave you short in the week a draw slips. Enter four weeks of expected money in and out, then delay a single receipt by one week and compare the lowest balance.
Use this when
- A large draw or customer payment is due and you are not confident about the date.
- Payroll, a supplier account or a subcontractor payment lands in the same week as an uncertain receipt.
- You want to show a bookkeeper, partner or lender exactly why timing matters.
Four-week cash forecast with one delayed receipt
Hypothetical starting values- Lowest closing balance, baseline
- $4,000.00 (week 1)
- Lowest closing balance, week 2 receipt delayed
- -$3,000.00 (week 2)
| Week | Receipts (delayed) | Outflows | Closing, baseline | Closing, delayed |
|---|---|---|---|---|
| 1 | $0.00 | $6,000.00 | $4,000.00 | $4,000.00 |
| 2 | $0.00 | $7,000.00 | $15,000.00 | -$3,000.00 |
| 3 | $18,000.00 | $8,000.00 | $7,000.00 | $7,000.00 |
| 4 | $9,000.00 | $5,000.00 | $11,000.00 | $11,000.00 |
Runs entirely in your browser. Nothing is saved, sent or written to any TALON account. Illustration only, not financial, tax or payroll advice.
How the arithmetic works
Each week starts with the previous week's closing balance. Closing balance equals opening balance plus receipts minus outflows. Week 1 opens with the starting cash you enter. The calculator reports the lowest closing balance in the four weeks and which week it occurs in.
The delay scenario moves the entire receipt in the week you choose into the following week. Nothing else changes. If you delay a week 4 receipt, it moves outside this four-week view. The calculator says so explicitly: the money is still expected, it simply falls after the horizon, so week 4 closes lower in this view.
What to enter as a receipt
Only enter money you realistically expect to clear into your account that week. An invoice you plan to send is not a receipt in the same week. A lender approval is not a receipt until funds are released. If a customer usually pays ten days after invoice, put the receipt in the week it usually clears, not the week you bill.
Outflows should include payroll, subcontractor payments, supplier bills you intend to pay, equipment payments, insurance, rent and owner draws. Leaving out owner pay makes the forecast look healthier than the business actually is.
Reading the result
Compare the two minimums. If the baseline minimum is comfortable but the delayed minimum goes negative or below the cushion you want to keep, that receipt is a single point of failure. Options worth considering include confirming the payment date in writing, moving a discretionary purchase, talking to a supplier about timing before the bill is due, or adjusting future draw milestones. These are planning prompts, not financial advice.
Step by step
- Enter the cash you actually have available today as starting cash.
- For each of four weeks, enter expected receipts and outflows. Use zero for empty weeks.
- Choose a receipt to delay by one week, or leave the delay off to see the baseline only.
- Compare baseline and delayed closing balances and the lowest projected balance.
- Download the results as CSV if you want to share them or keep them with your notes.
Common mistakes
- Counting an invoice or a lender approval as cash in the week it is issued.
- Leaving out owner draws, credit card payments or recurring overhead.
- Treating a four-week window as the whole picture when large bills land in week five.
- Delaying a week-4 receipt and assuming the money is gone. It is outside the window, not lost.
Limits of this resource
- Four weeks only, one delayed receipt, whole-dollar weekly buckets. It does not model partial receipts, interest, taxes or credit lines.
- Inputs are not saved or sent anywhere. This is an illustration, not financial, lending or tax advice.
Related resources
Related TALON pages
- TALON Cash Flow calendar — How TALON places receivables, payables and scheduled draws by date.
- TALON Sandbox — A saved what-if workspace for testing date changes over a longer horizon.
Connect field work to the books
TALON brings estimates, jobs, schedules and cash into one view for small builders and remodelers.