Construction change order template: prepare one change clearly
When a homeowner asks for something different, the hardest part is writing down exactly what changes, what does not, what it costs and how it affects the schedule. This worksheet helps you prepare one proposed change for review. Your actual change order document should follow your contract and local requirements.
CSV file, opens in spreadsheet apps. Contains: Field-by-field worksheet with scope, credits, cost lines, schedule effect and status. Plain cells, not an automated workbook; enter or recreate calculations using the instructions. Example rows are hypothetical. Free, no login.
Use this when
- A homeowner asks for an upgrade, addition or deletion during the job.
- You discover a hidden condition that changes the scope.
- You want the crew lead and office to agree on the change before it is priced.
Describe the change, not the conversation
Write the scope as if someone who was not at the site has to price and build it. "Owner wants the bigger window" is not a scope. "Replace planned 36 by 48 inch kitchen window with 48 by 48 inch unit, same manufacturer line; reframe rough opening; extend interior trim" is. Include what is removed from the original scope so you do not charge for both.
Record why the change exists: owner request, hidden condition, design error, code requirement identified by inspector. The reason often affects who pays and how the customer reacts, so state it neutrally and factually.
Price and schedule as separate decisions
Build the price from cost lines just like the original estimate: labor, materials, subs, equipment, disposal, then apply your margin. Show any credit for deleted work separately. State the effect on the schedule in days, and whether it affects other milestones or draws. A change that adds no dollars but adds a week is still a change.
- Price validity: state how long the price holds, especially when materials are volatile.
- Payment timing: whether the change is billed at approval, with the next draw or at completion, per your contract.
- Exclusions: what the change does not include, such as patching or painting adjacent areas.
Before anyone builds it
A prepared worksheet is a proposal, not an approval. Keep the status at Proposed until you have written approval in the form your contract requires. If you start work before approval, record that decision and who made it. Then add the change to your change order log so pending and approved totals stay separate.
Worked example
Hypothetical| Field | Entry |
|---|---|
| Change no. | CO-04 |
| Reason | Owner request |
| Added scope | 48x48 window, reframe opening, extend trim |
| Removed scope | Original 36x48 window (credit) |
| Price | $1,860 added, $640 credit, net $1,220 |
| Schedule | +2 working days, no draw change |
| Status | Proposed |
Step by step
- Give the change a number and date, and identify the job by address or job number rather than a person's name.
- Write the added scope, the removed scope and the reason.
- List inclusions and exclusions.
- Build cost lines and price, showing credits separately.
- State schedule effect in days and any milestones affected.
- Review internally, then present using your contract's change order document.
- Record the outcome in the change order log.
Common mistakes
- Starting the work on a verbal yes and pricing it afterwards.
- Forgetting to credit the original scope that the change replaces.
- Ignoring schedule effects because the price is small.
- Mixing several unrelated requests into one change so none can be approved separately.
Limits of this resource
- This is a preparation worksheet only. It is not a jurisdiction-specific contract form, does not create a binding agreement and makes no claim of legal validity.
- Consult your contract and a qualified professional about change order requirements in your area.
Change order preparation worksheet
talon-change-order-worksheet.csv
Related resources
Related TALON pages
- Contracts and terms — How TALON handles customer approval of contract documents.
- Job billing review — How approved change orders are billed without double-counting.
Connect field work to the books
TALON brings estimates, jobs, schedules and cash into one view for small builders and remodelers.